project brief
Volutpat curabitur pellen tesque parturient nibh congue quam mus. Semper ultricies nibh acut dolor cras. Elementum urna sed aliquam bibendum tempor adipiscing nulla.
category
client
ThemeFusion
start date
20240103
end date
20240410
budget
$ 1.3 Million
SRG Global is a leader in automotive coating products that needed a new paint fume exhaust system.
C-logic was contracted to:
- Complete scanning for topographical elevations and clearance issues
- Civil and structural engineering for a 200’ x 60’ platform and more than 150’ of trestles that extended back of over the existing plant to support 8’ diameter duct work
- Excavated and installed all footers and piers
- Fabricated and installed all steel including columns, beams, cross bracing, grating, handrail, trestles, Pipe supports, interior supports. This included a running (2) cranes at all times.
- Demolition of three rooftop structures that housed decommissioned equipment
- Project management over entire duration of this project
- All the work was completed on straight time except the switch over from the old Rash units to the new during a 2 week shutdown. This required close coordination with the plant to not interfere with production.The project was completed ahead of schedule and under budget with no issues.